C|24

C|24

Digidesign · 2005–2007 · Pro Audio

Mechanical engineering and industrial-design ownership of Digidesign's C|24: a low-profile console carried from surfaces and board interfaces through tooling, serviceability and production.

Mechanism Leadership Thermal Cost_Down
32 photos
Verified chronology

C|24 delivery chronology

2005–20078 decisive beats

  1. Read the project section ↓
  2. Read the project section ↓
  3. Read the project section ↓
DCD release sequence 7 checkpoints · 18 identifiers

Seven primary email checkpoints document 18 unique PCB DCD identifiers from April 18 through June 27, 2006.

  1. First verified DCD release packet Revision 1 geometry was delivered for twelve PCB identifiers.
  2. DCD coverage expanded Four more PCB identifiers entered the release set while four pending interfaces were called out explicitly.
  3. DCD revisions advanced Two remaining boards were added and ten controlled drawings advanced revision while unresolved inputs stayed visible.
  4. Eighteen-board DCD index The release status enumerated current revision levels across 18 unique PCB DCD identifiers.
  5. Encoder-board geometry revised DCD 9150-55153 reached revision 4 after holes were removed and tooling holes moved.
  6. Communications-board DCD revised DCD 9150-55198 advanced to revision 3.
  7. Automation-board DCD revised The Auto A drawing, 9150-55156, reached revision 4.
Complete dated index 25 events
  1. Kickoff and teardown The project opened with a request for a nonfunctional Control|24 unit to tear down and study before drawing the replacement.
  2. Architecture strategy locked The surface design and initial requirements were established, with only minor dimensional changes expected rather than a wholesale footprint change.
  3. DCD geometric-control system The construction review was canceled so the team could release Data Control Drawings as fast as possible and make the PCB-to-chassis interfaces explicit.
  4. First verified DCD release packet Revision 1 geometry was delivered for twelve PCB identifiers.
  5. DCD coverage expanded Four more PCB identifiers entered the release set while four pending interfaces were called out explicitly.
  6. DCD revisions advanced Two remaining boards were added and ten controlled drawings advanced revision while unresolved inputs stayed visible.
  7. Eighteen-board DCD index The release status enumerated current revision levels across 18 unique PCB DCD identifiers.
  8. Encoder-board geometry revised DCD 9150-55153 reached revision 4 after holes were removed and tooling holes moved.
  9. Communications-board DCD revised DCD 9150-55198 advanced to revision 3.
  10. Automation-board DCD revised The Auto A drawing, 9150-55156, reached revision 4.
  11. Phase 1 exit delivered The later delivered-milestone record places Phase 1 exit on October 21, 2006.
  12. Domestic fabrication bridge Mass Precision confirmed corrected revision models and PDFs while the bridge parts were already in process.
  13. Top-panel no-bid documented The March 7 status report records Kwanta's top-panel no-bid and the active Operations/Manufacturing response. By April 4, the matter was before Kwanta's board, with Mass Precision and Kenny identified as bridge options.
  14. Headphone-jack serviceability challenge Customer Service and Manufacturing challenged the jack replacement path. The April recessed mock-up was rejected; Erik subsequently designed the field-replaceable unit, a later outcome confirmed by his recollection and the July mounting-change form.
  15. Proto 3 build opened The delivered-milestone record places the Proto 3 build start on June 18.
  16. Proto 3 build completed The delivered-milestone record places Proto 3 completion on July 2.
  17. Side-cap paint-process inspection The July 5 table separately records side-cap length, distance outside drawing limits and flatness. A supplier comparison documents vertical Method A; ECO 12740 is a separate plastics production-release form.
  18. Release to manufacturing The delivered-milestone record marks release to manufacturing complete on August 16.
  19. Pilot build started Pilot build started August 20.
  20. Pilot build completed Pilot build completed August 31.
  21. Production started Production start was delivered September 6.
  22. At Risk to On Schedule Status moved from At Risk to On Schedule while the current First Customer Ship plan rebased from October 29 to November 7.
  23. First units delivered The first production units were delivered October 15.
  24. First Customer Ship First Customer Ship was delivered November 7, 2007. November 20 was the original Phase 1 plan, not the delivered milestone.
  25. Sustaining transition ECO 13707 was finalized and the team prioritized the next C|24 changes as project work shifted into sustaining support.
Derived intensity

Project entropy

A scored signal of complexity and recovery pressure over time, derived from source records and kept separate from documentary chronology.

9/10 peak · 21 signals
Peak records
9/10

CRITICAL: The status report records that Kwanta no-bid the Top Panel and that Operations and Manufacturing were seeking a resolution.

9/10

Headphone-jack serviceability challenged; the first recessed mock-up was rejected on ergonomic grounds before the later field-replaceable design.

9/10

Photo evidence: Gap check reveals significant shrinkage/interference in plastic fit.

Scored event index 21 records
Project entropy event scores and source references
DateScoreSignalSource
2/10 Initiated project by requesting legacy Control 24 unit to 'take apart and study'. RE_ Control 24.msg
4/10 Initial surface design drawn and PRD written; sent to mechanical for COGS estimate. FW_ current Curtis design.msg
5/10 Strategic decision: Abandon membrane switches for 'living-hinge' design; limit sheet metal to 39". _INTELLIGENCE_04_Engineering_meeting-notes.md
3/10 Released 'curtis_RC1_02_22_06.ai' artwork file to ID lead. ai file for curtis.msg
4/10 Cancelled construction review to prioritize release of Data Control Drawings (DCDs). RE_ C-24 refresh constructing review.msg
5/10 Released all internal small plastic parts to tooling. RE_ curtisPlastic Files are all 9440.msg
6/10 Phase 1 Exit Review deck dated October 23; its schedule page lists Phase 1 exit for October 23. Curtis Phase 1 Exit.ppt
7/10 Authorized Mass Precision to use offset welder for emergency manual sheet metal bridge. RE_ CURTIS COMMAND24 REV CONFIRMATION PLEASE.msg
9/10 CRITICAL: The status report records that Kwanta no-bid the Top Panel and that Operations and Manufacturing were seeking a resolution. Curtis.3.7.07.pdf
9/10 Headphone-jack serviceability challenged; the first recessed mock-up was rejected on ergonomic grounds before the later field-replaceable design. RE_ Potential Field_CS concern with current headphone design.msg
6/10 Delivered updated sheet metal drawings to VTech; vendor flags bending tool constraints. Subject: Re: DigiDelivery from Erik Norris: "C24 SHEETMETAL 04_26_07"
6/10 Vendor inspection record: a nine-unit C24 run started June 12; four units shipped June 30 and five were listed for July 4 shipment. 07_09_07_Digidesgin C24 pilot run inspection report 20070705.xls
8/10 Thermal failure: Side Caps 'unfit' due to mold/cure issues. 06_20_07_C-24 Part mold problem and action.pdf
8/10 Pilot Build Issues: Parts not straight, missing countersinks, paint cure time failure. 06_29_07_Curtis build issues_from_PingZ.pdf
7/10 Vendor admits 'bow' due to paint cure effect; lack of curing fixture identified. 06_29_07_C24_jetcrown_Reply from zw_07_03_07.pdf
9/10 Photo evidence: Gap check reveals significant shrinkage/interference in plastic fit. C24_gap_check.pdf
5/10 The August 15 status report scheduled RTM for August 16 and Pilot for August 22. Curtis.8.15.07.pdf
7/10 The October 3 status report marked FCS At Risk; its cover listed October 29 as the current plan. Curtis.10.3.07.pdf
6/10 Project Status recovered: 'On Schedule'. FCS set for 11/7. Curtis.10.24.07.pdf
4/10 Submitted ECOs for plastic parts (Sidecaps, Bolster, Meter Lens). C24_ECO_submitted-files.pdf
5/10 Finalized ECO 13707; planning transition for next year. Erik_Norris_weekly status reports.pdf
Documented revisions

Documented part revision records

Dates are taken from a drawing revision table or from the dated ECO document. They are not ECO approval dates or manufacturing-release dates. These two source-backed part histories illustrate documented revision activity and are not an exhaustive history of every project iteration; revision labels are recorded identifiers, with no assumption that a sequence is complete or consecutive.

14 2 parts
Part revision dates on one shared time axis 2 part rows with 14 marks from Apr 21, 2006 to Oct 30, 2007. Drawing-table dates use cyan squares; ECO-document dates use amber diamonds. 9150-55200-00 MicPre8 I/O assembly drawing 1 Revision 1, 2006-04-21. drawing revision table. Sources: LK-63a747ee 2 Revision 2, 2006-05-03. drawing revision table. Sources: LK-63a747ee 3 Revision 3, 2006-06-15. drawing revision table. Sources: LK-63a747ee 4 Revision 4, 2006-07-17. drawing revision table. Sources: LK-63a747ee 5 Revision 5, 2006-08-01. drawing revision table. Sources: LK-63a747ee 6 Revision 6, 2006-09-05. drawing revision table. Sources: LK-63a747ee 7 Revision 7, 2006-10-03. drawing revision table. Sources: LK-63a747ee 8 Revision 8, 2006-10-17. drawing revision table. Sources: LK-63a747ee 9 Revision 9, 2006-11-01. drawing revision table. Sources: LK-63a747ee 10 Revision 10, 2006-11-08. drawing revision table. Sources: LK-63a747ee 11 Revision 11, 2006-12-12. drawing revision table. Sources: LK-63a747ee 12 Revision 12, 2006-12-20. drawing revision table. Sources: LK-63a747ee 9420-56156-00 Jog wheel sheet-metal fabrication A Revision A, 2007-07-12. ECO 13082 records a REL action and shippable revision A.. Sources: LK-f2de03d1 B Revision B, 2007-10-30. ECO 13526 records a CHG action from A to B and shippable revision B; the mounting-hole tolerance changed to ±0.05 mm at the vendor's request.. Sources: LK-371b448c, LK-fa5c883a
Drawing revision table ECO document date
Revision dates and sources
PartRevisionDateDate basisRecord noteSources
9150-55200-00 MicPre8 I/O assembly drawing 1 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 2 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 3 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 4 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 5 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 6 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 7 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 8 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 9 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 10 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 11 drawing revision table Documented revision mark. LK-63a747ee
9150-55200-00 MicPre8 I/O assembly drawing 12 drawing revision table Documented revision mark. LK-63a747ee
9420-56156-00 Jog wheel sheet-metal fabrication A eco document ECO 13082 records a REL action and shippable revision A. LK-f2de03d1
9420-56156-00 Jog wheel sheet-metal fabrication B eco document ECO 13526 records a CHG action from A to B and shippable revision B; the mounting-hole tolerance changed to ±0.05 mm at the vendor's request. LK-371b448c, LK-fa5c883a
Forensic engineering case study of the Digidesign C|24 ("Curtis") — the RoHS-era successor to the Control|24 console.
Forensic Summary
Trigger

Replace the Control|24 with a lower-profile, RoHS-compliant console while integrating the controls, audio functions and production processes.

Intervention

Owned the mechanical implementation: surface development, board interfaces, molded and fabricated parts, serviceability, supplier build support and acceptance criteria.

Result

C24 reached First Customer Ship on November 7, 2007; the retrospective records Q4 FQA and revenue targets achieved alongside substantial launch-quality lessons.

C|24 (Curtis)

I. Project Summary

I owned the mechanical engineering and industrial-design implementation of Digidesign’s C|24, from the early surface and packaging work through tooling, build support and production release. The job was to turn a large, familiar control surface into a lower-profile product while preserving the feel and accessibility of a real mixing console.

The business brief was specific: replace the Control|24 with a RoHS-compliant product, package sixteen Digidesign preamps in place of the licensed design, support 5.1 monitoring, and fit within a 43-inch maximum width. Removing the approximately $200 royalty was a program objective. My responsibility was the physical product that made those changes possible: surfaces, molded parts, fabricated chassis, board interfaces, controls, artwork and the instructions suppliers needed to build and inspect them.

II. The Product That Shipped

The C|24 put twenty-four motorized faders, sixteen preamps, a stereo submixer and surround-monitor controls into one low-profile console. Most analog connections moved to DB25 connectors. Three two-row LCDs replaced the predecessor’s short channel readouts, and the control layout consolidated functions that had occupied dedicated buttons. The product and hardware teams defined the feature set; I developed and integrated its physical implementation.

That integration reached below the visible surface. The March 2006 construction-review email records my solution for getting the meter boards inside the sheet-metal enclosure while preserving the plastic design I wanted. Once that packaging problem was resolved, I redirected the review time toward releasing the Data Control Drawings that the PCB designers needed. Surface development and electrical packaging advanced together.

I also designed and built the new two-encoder surround-panning interface: an X/Y control that let an engineer position a sound across a 5.1 field by feel. The side caps, gills, meter windows, jog-wheel surround and front bolster gave that dense control layout a continuous exterior. Their appearance depended on the geometry and assembly underneath them.

III. Design and Production

1. Paint Curing and Side-Cap Fit

The long ABS side caps exposed the interaction between molding, paint curing and assembly fit. Jetcrown’s comparison shows the original unsupported baking arrangement, an attempted three-support fixture that still allowed twisting, and Method A, which held the parts vertically to reduce deformation. I worked the problem through the supplier’s process and the mating geometry.

The July 5 inspection table shows why the diagnosis mattered. One left-side-cap sample lost 1.04 mm in length through painting, from 755.28 to 754.24 mm, ending 2.27 mm below the lower drawing limit. The same inspection tracked flatness separately. Cure support could address deformation, while the part’s final size and mating geometry still needed their own decisions.

I released the plastics for production through ECO 12740, including mechanical changes to both side caps. Supplier process work continued alongside the part revisions. Getting the plastics into production also required agreement on which dimensions controlled fit and which could be relaxed.

2. Recovering Top-Panel Fabrication

The main panel combined large fabricated surfaces with densely placed welded hardware. By March 7, 2007, the status report recorded Kwanta’s no-bid and an active Operations and Manufacturing response. The April report identified Mass Precision and Kenny as bridge options within the VTech manufacturing program.

I worked with Mass Precision on manual offset-welded parts and supported the overseas fabrication path while welding capability and panel quality were being resolved. The geometry still had to work at the factory: access for the welding head, placement of the studs, countersinks, bend quality and the cosmetic surface all belonged to the same part.

I fully ruptured my Achilles during this period. After returning from the hospital, I sent the weld-stud files from the hotel so fabrication could continue. The work progressed, but the later lessons-learned report also records the cost of working outside the normal file-control system: an incongruent revision reached the manufacturer.

3. A Quiet, Low-Profile Console

The C|24 requirements explicitly prohibited a fan because the console sits at the mix engineer’s listening position. They also specified an external power supply, replacing the Control|24’s internal supply. Moving power conversion outside the console and consolidating the rear-panel connections helped make the lower-profile enclosure possible.

The specified operating environment was 10–35 °C. Cooling and packaging had to work within that requirement while keeping the listening position quiet.

4. A Field-Replaceable Headphone Jack

The proposed front jack location put the headphone plug where it could be struck, while the original assembly made replacement unnecessarily invasive. Arndt Hufenbach and Manufacturing pushed for service access, and I developed the mechanical response.

The first recessed-bolster mock-up did not settle the matter. In April, product management rejected it because different headphone-plug overmolds made the recess awkward to use. Several PMs remained strongly opposed to a replaceable jack. Arndt, Manufacturing and I continued pressing the issue, and I designed the field-replaceable unit that ultimately shipped.

The July mounting-change form and the earlier rejected mock-up describe different stages of that work. The engineering lesson is the negotiation between access, protection, appearance and serviceability, carried through to a physical solution.

5. Board-to-Mechanical Interfaces

I controlled C|24 board interfaces through Data Control Drawings. The June register lists 19 distinct PCBA designs; the MicPre8 I/O drawing records 12 revisions.

I used Data Control Drawings to make those interfaces explicit: board outlines, mounting holes, component locations and clearances that electrical layout had to respect. The MicPre8 I/O drawing reached revision 12. Its revision table records changes to mounting holes, headers, connector spacing and the board outline, with my name against the revisions. The point was to resolve those changes against the assembly while the design was still editable.

The drawing releases gave PCB layout and mechanical tooling a common set of interfaces as both designs evolved.

6. Power-Supply Certification

The external supply created a separate release dependency. The July status report planned to hand-pack the first hundred supplies and apply UL labels at Menlo Park, while a later enclosure variant remained subject to thermal work.

Engineering worked with UL to start system and supply certification in parallel. The post-project lessons identify that as a successful change to the NPI process. Mechanical release, hardware validation, certification and the final pack-out had to converge for shipment.

7. Controls and Molded-Part Geometry

The smaller Bourns EM14 encoder needed its own mechanical integration. I designed the jog-wheel support and surround so the component, knob and adjacent surface worked as an assembly. ECO 13082 records the bracket release. ECO 13526 later relaxes its mounting-hole tolerance to ±0.05 mm at the vendor’s request, making the drawing compatible with the fabrication process.

The gills required careful surface development and dimensional inspection against the side caps. The molded parts also brought short shots, drag, sinks, gate placement and interference around the faders. The June issue list separates completed corrections from open questions and temporary trim-to-fit measures. In sustaining work, I also supported foam sealing around the meter-lens area to address dust ingress.

IV. Production Acceptance and Release

I carried the mechanical model through supplier files, drawing releases, inspection and assembly feedback. The record includes the plastics and artwork, the sheet-metal structure, small controls and light-management parts, and the changes needed after those pieces met on the line. The work extended into sustaining changes after First Customer Ship.

Inspection criteria were part of that engineering responsibility. In November I originated deviation DEV00118 to remove noncritical dimensions and increase selected tolerances, with acceptance tied to named Jetcrown inspection reports. It covered side caps, the bolster, meter parts and gills. The decision preserved what controlled fit and function and made acceptable production variation explicit.

The lessons-learned record is candid about the broader launch. It credits meeting Q4 FQA and revenue targets and getting costs below the Phase 1 target. It also records revision confusion, late board changes, cosmetic quality problems and inadequate spare-parts coverage. Mechanical control had to include the files, the supplier’s understanding and the inspection decision, as well as the CAD.

V. Results

  • Product mandate: twenty-four faders, sixteen preamps and a 43-inch maximum width; removal of the approximately $200 licensed-design royalty.
  • Mechanical integration: nineteen distinct PCBA designs in the June build register; twelve documented revisions of the MicPre8 I/O drawing.
  • Serviceability: a field-replaceable headphone-jack assembly, developed despite resistance to changing the original design.
  • Manufacturing: a manual-fabrication bridge, documented cure-support alternatives and explicit acceptance criteria for production plastics.
  • Delivery: First Customer Ship on November 7, 2007. The project retrospective records that the Q4 FQA and revenue targets were achieved.

The July financial plan estimated a 51.8% gross margin at an $8,995 suggested retail price. The later product-master approval set the price at $9,995.

VI. Market Context & Legacy

The C|24 offered a substantial physical console below the ICON range: twenty-four faders, audio front-end functions and monitor control in one product. Kevin Becka’s February 2008 field test connects the external power supply and DB25 conversion to the lower-profile design, and describes using the two-encoder surround panner. His review also records real tradeoffs, including LCD viewing angle and the loss of a dedicated numeric keypad. Mix field test.

The hardware had a long supported life. Avid lists final sale on December 31, 2017 and end of support on December 31, 2022. Neyrinck’s current documentation describes third-party C|24 support through V-Control Pro, extending its software options beyond Avid’s product cycle. Avid lifecycle record, V-Control Pro documentation.

VII. Source Trail

The engineering account draws on the Curtis hardware PDD, the June PCBA build register, original project emails, drawing revision tables, vendor inspection and fixture records, ECOs, the November delivery schedule and the post-project lessons learned. The manufacturing photographs below show the actual parts and their interfaces. The economic figures retain the dates and assumptions of their source snapshots.

Cast & Credits

Mechanical & Industrial Design · 3

Neal Breitbarth Mechanical/ID Lead
Mark Sires Mechanical Engineer
Jonathan Eccles Industrial Design (Early Phase)

Hardware Engineering · 2

Robin Parnaby Hardware Engineering Lead
David Anthony Hardware Engineer

PCB Design · 2

Franco Piccininni PCB Design
Greg Vieyra PCB Design

Firmware & Software · 3

Ethan Grossman Firmware Engineer
Eamonn Fay Firmware Engineer
Mari Matsuo Software ETS

Manufacturing Operations · 4

Kerwin Yuen Manufacturing Engineer
Ed Bangert Manufacturing Engineer
Ping Zhang Manufacturing Engineer
Roger Lau Manufacturing Engineer

Test & Quality Assurance · 4

Matt Peterson HW ETS
Bill Latham HW ETS
Josh Bingham HW ETS
Craig Presnell Quality Assurance

Purchasing · 2

Terri Merrell Senior Buyer/Planner
Dena Goldberg Purchasing

Program & Product Management · 3

Michael Moskowitz Program Manager
Matt Cho Program Manager
Stan Cotey Product Manager

Product Marketing · 2

Greg Westall Product Marketing
Lev Perrey Product Marketing Manager

Technical Publications · 2

Don Falcone Tech Pubs
Tom Dambly Tech Pubs

Customer Service · 2

Arndt Hufenbach Customer Service
Vicky Moreno Customer Service

Other · 1

NewDealDesign Graphic overlay & LE-look aesthetic, early 2006
External · Vendors & Partners

VTech · 2

Henry Lee Vendor Contact
Ben Ho Vendor Contact

Jetcrown · 2

ZW Vendor Contact
Warren Man Vendor Lead

Mass Precision · 2

Ed Stegall Fabrication Contact
Fidel Saucedo Programming Contact

Breakout composition · system → intervention → record

Visual Evidence

Prototype assemblies, supplier process photographs and released drawings show how the console took shape.

Origin Story· 9

Prototype console with the control-panel structure exposed before final exterior assembly.
Prototype console with the control panel structure exposed before final exterior assembly.
Front corner of the prototype, showing the bolster interface and sheet-metal side structure.
Front corner of the prototype, showing the bolster interface and sheet metal side structure.
Interior view of the metal enclosure and board mounting geometry.
Interior view of the metal enclosure and board mounting geometry.
Side structure before the molded side cap is fitted.
Side structure before the molded side cap is fitted.
Prototype side cap fitted over the metal structure, showing the long side profile.
Prototype side cap fitted over the metal structure, showing the long side profile.
Meter-board and lens interfaces above the prototype control surface.
Meter board and lens interfaces above the prototype control surface.
Open front-bolster end and its interface with the fader-panel structure.
Open front bolster end and its interface with the fader panel structure.
Side-profile design rendering, showing the gill and the rise into the meter bridge.
Side profile design rendering, showing the gill and the rise into the meter bridge.
Design rendering of the complete control surface and exterior part relationships.
Design rendering of the complete control surface and exterior part relationships.

Side Cap Crisis· 5

Paired side caps showing visible bow along their length.
Paired side caps showing visible bow along their length.
Unsupported horizontal cure arrangement documented in the supplier fixture comparison.
Unsupported horizontal cure arrangement documented in the supplier fixture comparison.
Vertical Method A cure-support arrangement in the supplier comparison.
Vertical Method A cure support arrangement in the supplier comparison.
July 5 before-and-after-paint inspection table: length, distance outside tolerance and flatness are separate columns.
July 5 before and after paint inspection table: length, distance outside tolerance and flatness are separate columns.
ECO 12740: Erik Norris originated the plastics production release; the form identifies mechanical changes to both side caps.
ECO 12740: Erik Norris originated the plastics production release; the form identifies mechanical changes to both side caps.

Manufacturing Wins· 4

Jetcrown dimensional inspection of the gill and side-cap geometry, with measured values marked on the views.
Jetcrown dimensional inspection of the gill and side cap geometry, with measured values marked on the views.
MicPre8 I/O Data Control Drawing at revision 12: board geometry, mounting and connector relationships.
MicPre8 I/O Data Control Drawing at revision 12: board geometry, mounting and connector relationships.
Fabricated control-panel bend and adjacent artwork under cosmetic review.
Fabricated control panel bend and adjacent artwork under cosmetic review.
Close-up of a panel bend beside the modifier-key artwork.
Close up of a panel bend beside the modifier key artwork.

Structural Components· 5

Supplier-marked molding defects: drag and short-shot areas on the side-cap ribs.
Supplier marked molding defects: drag and short shot areas on the side cap ribs.
June build issue list separating observed problems, causes and proposed or completed corrective actions.
June build issue list separating observed problems, causes and proposed or completed corrective actions.
Bourns EM14 supplier dimensional drawing used for encoder integration.
Bourns EM14 supplier dimensional drawing used for encoder integration.
July 16 fit-check photograph of the front-bolster and side-cap joint.
July 16 fit check photograph of the front bolster and side cap joint.
July 16 fit check at the meter-window structure and surrounding molded parts.
July 16 fit check at the meter window structure and surrounding molded parts.

Paper Trail· 6

Side-cap measurement sketch identifying where to check the gap.
Side cap measurement sketch identifying where to check the gap.
MicPre8 I/O revision table: twelve recorded revisions, with Erik Norris named against the changes.
MicPre8 I/O revision table: twelve recorded revisions, with Erik Norris named against the changes.
ECO 12262 cover sheet for the C24 small-plastics release.
ECO 12262 cover sheet for the C24 small plastics release.
ECO 12263 cover sheet for sheet-metal parts and artwork release.
ECO 12263 cover sheet for sheet metal parts and artwork release.
ECO 12263 detail sheet listing the released materials and revisions.
ECO 12263 detail sheet listing the released materials and revisions.
ECO 12993 records the July headphone-jack mounting change.
ECO 12993 records the July headphone jack mounting change.

Press Resources· 3

C24 installed in a studio desk.
C24 installed in a studio desk.
Finished C24 control layout, showing the fader banks, displays and right-hand controls.
Finished C24 control layout, showing the fader banks, displays and right hand controls.
C24 user-guide cover, version 7.4.
C24 user guide cover, version 7.4.

Interactive Model

Explore the 3D model

Open model file ↗

This page is rendered from the canonical record for this project. The source and build system are documented in the EN-OS colophon.